This scheme will help alleviate serious flooding of Bandon Town. It has taken a number of years for the scheme to go through feasibility, planning & procurement processes and construction prior to becoming operational.
There are 5 distinct stages involved in OPW Flood Relief Schemes;
Stage 1: Feasibility & Preferred Option Selection.
Stage 2: Environmental Assessment & Planning.
Stage 3: Detailed design, tender process & award of construction contract.
Stage 4 & 5: Construction & Handover.
The following Consultancy Firms were appointed in November 2011 by the OPW to advance the Bandon Flood Relief Scheme; Byrne Looby Partners Water Services Ltd. in association with JBA Consulting – Engineering Consultants. Ryan Hanley in partnership with McCarthy Keville O'Sullivan Ltd. - Environmental Consultants.
Public Exhibition Documents are available for all to view on the following website http://www.bandonfloodwarning.ie/bandonfloodrelief.htm